Title:
|
Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 4 to Contract 46-06 (K6-049), City Hall Data Center Improvements, Ricchio, Inc., contractor.
Recommendation: Change Order No. 4 on Contract 46-06 (K6-049), City Hall Data Center Improvements, Ricchio, Inc., contractor, as submitted, be approved in the amount of $6,598.00.
Further recommends that funding to defray the cost of this change order be appropriated from Account 987.100.5030, City Hall-IS Computer Room HVAC.
Fiscal Note: Funds are available as herein delineated.
|