Legislation Details

File #: 0547-26    Version: A Name: Subject: Consideration of Change Order No. 2 on Contract W-23-7, 42 Inch Water Main - Phase 3, Mound Avenue to Main Street, Super Excavators, Inc (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $1
Type: Communication Status: In Committee
File created: 6/10/2026 In control: Waterworks Commission
On agenda: Final action:
Title: Subject: Consideration of Change Order No. 2 on Contract W-23-7, 42 Inch Water Main - Phase 3, Mound Avenue to Main Street, Super Excavators, Inc (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $147,874.00, bringing the contract total to $18,368,234.00.
Attachments: 1. 2026.06.17 - W-23-7 Change Order 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Subject: Consideration of Change Order No. 2 on Contract W-23-7, 42 Inch Water Main - Phase 3, Mound Avenue to Main Street, Super Excavators, Inc (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an increase of $147,874.00, bringing the contract total to $18,368,234.00.