Title:
|
Change Order No. 3 on Contract 20150019, Lake Michigan Pathway Phase lll
Resolved, that Change Order No. 3 on Contract 20150019, Lake Michigan Pathway Phase lll, Ray Hintz, Inc., contractor, as submitted, is approved in the deduct amount of ($76,510.34).
Fiscal Note: The below Org-Objects be adjusted in the following amounts.
($15,302.07) - Org-Object 45040-57550, DPW-Lake Michigan Pathway
($61,208.27) - Org-Object 2031-57550, State’s Share Lake MI Pathway
($76,510.34) - Total
|