Sponsor
Alderman Weidner
Title
Submission of bid results on Contract 44-11 (K1-046), Sidewalk Replacement, Phase II.
Resolved, that Contract 44-11 (K1-046), 2011 Sidewalk Replacement, Phase II, be awarded to AZAR LLC, Racine, WI, at their bid price of $132,814.90, they being the lowest responsible bidder.
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
$ 112,814.90 - Account 906.000.5520, Sidewalk Replacement
$ 10,000.00 - Account 991.908.5520, Sidewalk Replacement
$ 5,000.00 - Account 991.908.5320, Replacement Curb & Gutter
$ 5,000.00 - Account 991.908.5530, Crosswalk Ramps
$ 132,814.90 - Total
Fiscal Note: Funds are available as herein delineated.