File #: Res.0092-16    Version: A Name: Change Order No. 1 on Contract 20150006, 2015 Street & Alley Paving - Southside Assessable (R1)
Type: Resolution Status: Passed
File created: 3/15/2016 In control: City Attorney's Office
On agenda: 3/15/2016 Final action: 3/15/2016
Title: Change Order No. 1 on Contract 20150006, 2015 Street & Alley Paving - Southside Assessable (R1) Resolved, that Change Order No. 1 on Contract 20150006, 2015 Street & Alley Paving - Southside Assessable (R1), LaLonde, Inc., contract, as submitted is approved in the amount of $83,907.48. Fiscal Note: Funding to defray the cost of the change order be appropriated from the below Org-Objects: $51,055.52 - Org-Object 45040-57500, Concrete Street Paving Misc. $20,000.00 - Org-Object 45040-57500, Concrete Alley Paving Misc. $12,851.96 - Org-Object 60484-57570, Storm Sewer, Misc. Locations. $83,907.48 - Total
Sponsors: James Morgenroth
Related files: 0182-16

Sponsor

Alderman Morgenroth

 

Title

Change Order No. 1 on Contract 20150006, 2015 Street & Alley Paving - Southside Assessable (R1)

 

Resolved, that Change Order No. 1 on Contract 20150006, 2015 Street & Alley Paving - Southside Assessable (R1), LaLonde, Inc., contract, as submitted is approved in the amount of $83,907.48.

 

Fiscal Note: Funding to defray the cost of the change order be appropriated from the below Org-Objects:

 

$51,055.52 - Org-Object 45040-57500, Concrete Street Paving Misc.

$20,000.00 - Org-Object 45040-57500, Concrete Alley Paving Misc.

$12,851.96 - Org-Object 60484-57570, Storm Sewer, Misc. Locations.

$83,907.48 - Total