Subject: Communication sponsored by Alder McCarthy, on behalf of the Waterworks Commission, requesting the approval of a Developer's Agreement for the 90th St. Water Main Extension Development Project (Village of Mount Pleasant, developer).
Recommendation of the Waterworks Commission on 08-15-2023: To Approve with Referral to Finance & Personnel Committee.
Recommendation of the Finance and Personnel Committee on 08-28-2023: That the Waterworks Commission be granted approval to accept a Developer's Agreement for the 90th St. Water Main Extension Development Project (Village of Mount Pleasant, developer).