Sponsor
Alderman Kaplan
Title
Change Order No. 1 on Contract 17-14 (K4-017), Racine Streambank Stabilization
Resolved, that Change Order No. 1 on Contract 17-14 (K4-017), Racine Streambank Stabilization, Native Construction, contractor, as submitted, is approved in the amount of $117,268.23.
Fiscal Note: Funding to defray the cost of this change order be appropriated from the following accounts:
$ 55,572.75 - Account 104.993.5430, Wash Pk Streambank A, UNP (Spring St.)
$ 61,695.48 - Account 104.993.5440, Wash Pk Streambank B, (Washington Pk)
$117,268.23 - Total