File #: 10-4724    Version: A Name: Change Order No. 1 on Contract 44-09 (K9-045), Storm & Sanitary CIPP Lining & Manhole Repair
Type: Communication Status: Passed
File created: 2/2/2010 In control: Public Works and Services Committee
On agenda: Final action: 2/16/2010
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/ Engineering submitting Change Order No. 1 on Contract 44-09 (K9-045), Storm & Sanitary CIPP Lining & Manhole Repair, Visu-Sewer Clean and Seal, Inc., contractor. (Res.10-1874) Recommendation of the Public Works and Services Committee on 2-9-10: That Change Order No. 1 on Contract 44-09 (K9-045), Storm & Sanitary CIPP Lining & Manhole Repair, Visu-Sewer Clean & Seal, Inc., contractor, as submitted, be approved in the deduct amount of $87,975.42. Fiscal Note: Change Order No. 1 will result in a decrease in contract price.
Attachments: 1. Ald Helding - CO 1-44-09, 2. CO #1 - 44-09
Related files: Res.10-1874
Title
Subject: (Direct Referral)  Communication from the Assistant Commissioner of Public Works/ Engineering submitting Change Order No. 1 on Contract 44-09 (K9-045), Storm & Sanitary CIPP Lining  & Manhole Repair, Visu-Sewer Clean and Seal, Inc., contractor.  (Res.10-1874)
 
Recommendation of the Public Works and Services Committee on 2-9-10: That Change Order No. 1 on Contract 44-09 (K9-045), Storm & Sanitary CIPP Lining & Manhole Repair, Visu-Sewer Clean & Seal, Inc., contractor, as submitted, be approved in the deduct amount of $87,975.42.
 
Fiscal Note:  Change Order No. 1 will result in a decrease in contract price.