Title: Change Order for 2007 City Resurfacing Contract Resolved, that Change Order No. 1 on Contract 26-07 (K7-030), 2007 City Resurfacing, A. W. Oakes & Son, contractor, as submitted, be approved in the amount of $17,959.40. Further resolved, that funding to defray the cost of this change order be appropriated from Account 987.908.5130, Asphalt Resurfacing. Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 07-1434

Sponsor

Alderman Hart

 

Title

Change Order for 2007 City Resurfacing Contract

 

 

Resolved, that Change Order No. 1 on Contract 26-07 (K7-030), 2007 City Resurfacing, A. W. Oakes & Son, contractor, as submitted, be approved in the amount of $17,959.40.

 

Further resolved, that funding to defray the cost of this change order be appropriated from Account 987.908.5130, Asphalt Resurfacing.

 

 