Ricine Banner
File #: 12-7727    Version: A Name: Bid results on Contract 38-12 (K2-043), Sewer and Lateral Lining. (Res. 12-3169)
Type: Communication Status: Passed
File created: 5/17/2012 In control: Public Works and Services Committee
On agenda: Final action: 6/4/2012
Title: Subject: Communication from the Commissioner of Public Works submitting bid results on Contract 38-12 (K2-043), Sewer and Lateral Lining. (Res. 12-3169) Recommendation of the Public Works and Services Committee on 5-29-12: That Contract 38-12 (K2-043), Sewer and Lateral Lining, be awarded to Musson Brothers, Inc., Rhinelander, WI, at their bid price of $638,425.95, they being the lowest responsible bidder. Fiscal Note: Funding to defray the cost of this public works project be appropriated from the following accounts: $ 320,086.20 - Account 287.992.5310, Sanitary Sewers, Misc. Loc. $ 18,339.75 - Account 104.992.5420, Storm Sewer, Misc. Loc. $ 300,000.00 - Water & Wastewater Utility $ 638,425.95
Attachments: 1. 38-12 Bid Results.pdf, 2. 38-12
Related files: Res.12-3169
Title
Subject: Communication from the Commissioner of Public Works submitting bid results on Contract 38-12 (K2-043), Sewer and Lateral Lining. (Res. 12-3169)
 
Recommendation of the Public Works and Services Committee on 5-29-12: That Contract 38-12 (K2-043), Sewer and Lateral Lining, be awarded to Musson Brothers, Inc., Rhinelander, WI, at their bid price of $638,425.95, they being the lowest responsible bidder.
 
Fiscal Note: Funding to defray the cost of this public works project be appropriated from the following accounts:
 
$ 320,086.20 - Account 287.992.5310, Sanitary Sewers, Misc. Loc.
$   18,339.75 - Account 104.992.5420, Storm Sewer, Misc. Loc.
$ 300,000.00 - Water & Wastewater Utility
$ 638,425.95