Title: Subject: Direct Referral. Communication from the Commissioner of Public Works/City Engineer submitting bid results on Contract 17-07 (K7-020), Sidewalk Replacement - Phase I (R1). Recommendation: Contract 17-07 (K7-020), Sidewalk Replacement - Phase I (R1), be awarded to D.C. Burbach, Inc., Waukesha, WI, at their bid price of $236,608.00, they being the lowest responsible bidder. Further recommends that funding to defray the cost of this public works project be appropriated from the following accounts: $231,608.00 - Account 906.000.5520, Sidewalk Replacement $ 5,000.00 - Account 987.908.5520, Sidewalk Replacement $236,608.00 - Total Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 17-07 Bid Results.pdf, 2. 17-07 Bid Tab.pdf
Related files: Res.07-0166
Title
Subject: Direct Referral. Communication from the Commissioner of Public Works/City Engineer submitting bid results on Contract 17-07 (K7-020), Sidewalk Replacement - Phase I (R1).
 
Recommendation: Contract 17-07 (K7-020), Sidewalk Replacement - Phase I (R1), be awarded to D.C. Burbach, Inc., Waukesha, WI, at their bid price of $236,608.00, they being the lowest responsible bidder.
 
Further recommends that funding to defray the cost of this public works project be appropriated from the following accounts:
 
$231,608.00 - Account 906.000.5520, Sidewalk Replacement
$    5,000.00 - Account 987.908.5520, Sidewalk Replacement
$236,608.00 - Total
 
Fiscal Note: Funds are available as herein delineated.