File #: Res.13-0042    Version: A Name: Change Order No. 1 to Contract 27-12 (K2-031), CCTV & Manhole Inspection
Type: Resolution Status: Passed
File created: 2/5/2013 In control: City Attorney's Office
On agenda: Final action: 2/5/2013
Title: Change Order No. 1 to Contract 27-12 (K2-031), CCTV & Manhole Inspection Resolved, that Change Order No. 1 on Contract 27-12 (K2-031), CCTV & Manhole Inspection, Green Bay Pipe & TV, contractor, is approved in the deduct amount of ($6,604.40). Fiscal Note: Change Order No. 1 will result in a decrease in contract price. Funding accounts to be adjusted by the following amounts: ($ 6,203.20) - Account 104.992.5420, Storm Sewers, Misc. Loc. ($ 401.20) - Account 287.992.5310, Sanitary Sewers, Var. Loc. ($ 6,604.40) - Total
Sponsors: Sandy Weidner
Related files: 13-8556
Sponsor
Alderman Weidner
 
Title
Change Order No. 1 to Contract 27-12 (K2-031), CCTV & Manhole Inspection
 
Resolved, that Change Order No. 1 on Contract 27-12 (K2-031), CCTV & Manhole Inspection, Green Bay Pipe & TV, contractor, is approved in the deduct amount of ($6,604.40).
 
Fiscal Note: Change Order No. 1 will result in a decrease in contract price. Funding accounts to be adjusted by the following amounts:
($ 6,203.20) - Account 104.992.5420, Storm Sewers, Misc. Loc.
($ 401.20) - Account 287.992.5310, Sanitary Sewers, Var. Loc.
($ 6,604.40) - Total