Title:
|
Subject: Communication sponsored by Alder Harmon, submitting Change Order No. 2 to Contract 2025005 - 2025 Sanitary Sewer Main CIPP Linings, Visu-Sewer, Contractor.
Staff Recommendation to the Public Works and Services Committee on 08.25.26: That Change Order No. 2 to Contract 2025005 - 2025 Sanitary Sewer Main CIPP Linings, Visu-Sewer, Contractor, be approved in the deduct amount of ($175,665.25).
Fiscal Note: Funding for this change order is credited in following Org-Objects:
($166,246.50) 22640 57560 Sanitary Sewer
($3,698.75) 60484 57570 Storm Sewers
($5,720.00) 40102 57560 R.W.W.U.
($175,665.25) Total
|