Ricine Banner
File #: Res.15-0092    Version: A Name: Change Order No. 1 on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1)
Type: Resolution Status: Passed
File created: 3/3/2015 In control: City Attorney's Office
On agenda: Final action: 3/3/2015
Title: Change Order No. 1 on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1) Resolved, that Change Order No. 1 on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1), AZAR, LLC., contractor, as submitted, is approved in the amount of $58,563.58. Fiscal Note: Funding to defray the cost of the change order be appropriated from the following accounts: $10,286.52 - Org-Object 22450-57110, Cemetery Roads and Walks $48,277.06 - Org-Object 40104-57515, Assessable Project Sidewalks $58,563.58 - Total
Sponsors: Jim Kaplan
Related files: 15-00137
Sponsor
Alderman Kaplan
 
Title
Change Order No. 1 on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1)
 
Resolved, that Change Order No. 1 on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1), AZAR, LLC., contractor, as submitted, is approved in the amount of $58,563.58.
 
Fiscal Note: Funding to defray the cost of the change order be appropriated from the following accounts:
 
$10,286.52 - Org-Object 22450-57110, Cemetery Roads and Walks
$48,277.06 - Org-Object 40104-57515, Assessable Project Sidewalks
$58,563.58 - Total