File #: 0799-23    Version: A Name: Subject: Final Payment Request on Contract W-23-3, 2023 Lead Service Replacements, Reesman's Excavating & Grading (Contractor) Recommendation: To Approve Fiscal Note: Contract W-23-3 is complete at a final cost of $275,311.13. Utility to pay Contrac
Type: Communication Status: Passed
File created: 8/4/2023 In control: Waterworks Commission
On agenda: Final action: 8/15/2023
Title: Subject: Final Payment Request on Contract W-23-3, 2023 Lead Service Replacements, Reesman's Excavating & Grading (Contractor) Recommendation: To Approve Fiscal Note: Contract W-23-3 is complete at a final cost of $275,311.13. Utility to pay Contractor retainage amount of $6,968.13.
Attachments: 1. w-23-3_req for final pmt_ltr to comsrs

Title

Subject: Final Payment Request on Contract W-23-3, 2023 Lead Service Replacements, Reesman's Excavating & Grading (Contractor)

 

Recommendation: To Approve

 

Fiscal Note: Contract W-23-3 is complete at a final cost of $275,311.13. Utility to pay Contractor retainage amount of $6,968.13.