File #: Res.14-0025    Version: A Name: Change Order No. 2 on Contract 7-13 (K3-007), Johnson Park Streambank Stabilization
Type: Resolution Status: Passed
File created: 1/21/2014 In control: City Attorney's Office
On agenda: Final action: 1/21/2014
Title: Change Order No. 2 on Contract 7-13 (K3-007), Johnson Park Streambank Stabilization Resolved, that Change Order No. 2 on Contract 7-13 (K3-007), Johnson Park Streambank Stabilization, Native Construction, contractor, is approved in the amount of $39,131.69. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $46,297.69 - Account 104.992.5470, Lincoln Park Streambank Stabilization ($7,166.00) - Account 107.000.5750, Land Improvement Fiscal Note: Funds are available as herein delineated.
Sponsors: Sandy Weidner
Related files: 14-9697
Sponsor
Alderman Weidner
 
Title
Change Order No. 2 on Contract 7-13 (K3-007), Johnson Park Streambank Stabilization
 
Resolved, that Change Order No. 2 on Contract 7-13 (K3-007), Johnson Park Streambank Stabilization, Native Construction, contractor, is approved in the amount of $39,131.69.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$46,297.69 - Account 104.992.5470, Lincoln Park Streambank Stabilization
($7,166.00) - Account 107.000.5750, Land Improvement
 
Fiscal Note: Funds are available as herein delineated.