Title
Subject: (Direct Referral) Communication from the Interim Commissioner of Public Works/Operations submitting Change Order No. 3 to Contract 1-11 (K1-001), City Hall Renovations-Phase III (R1), Seater Construction Co., Inc., contractor. (Res. 11-2646)
Recommendation of the Public Works and Services Committee on 6-28-11: That Change Order No. 3 on Contract 1-11 (K1-001), City Hall Renovations-Phase III (R1), Seater Construction Co., Inc., contractor, be approved in the amount of $34,025.00.
Further recommends that funding to defray the cost of this change order be appropriated from Account 990.100.5010, City Hall-Facilities Plan Implementation.