File #: Res.06-7014    Version: A Name: FINAL PAYMENT MAIDEN LANE STORM SEWER IMPROVEMENTS
Type: Resolution Status: Passed
File created: 5/2/2006 In control: City Attorney's Office
On agenda: Final action: 5/2/2006
Title: FINAL PAYMENT MAIDEN LANE STORM SEWER IMPROVEMENTS RESOLVED, that the work performed by Willkomm Excavating & Grading, Inc., on Contract 21-05 (K6-028), Maiden Lane Storm Sewer Improvements, be accepted and final payment authorized for a total contract amount of $236,217.92. FISCAL NOTE: Contract was authorized under Resolution No. 6495 of May 15, 2005.
Sponsors: Ronald Hart
Related files: 06-1823

Sponsor

Alderman Hart

 

Title

FINAL PAYMENT MAIDEN LANE STORM SEWER IMPROVEMENTS

 

 

RESOLVED, that the work performed by Willkomm Excavating & Grading, Inc., on Contract 21-05 (K6-028), Maiden Lane Storm Sewer Improvements, be accepted and final payment authorized for a total contract amount of $236,217.92.

 

                      