File #: Res.0424-17    Version: A Name: Change Order No. 1 on Contract 20170051, Samuel Myers Park Restorations - Phase IV
Type: Resolution Status: Passed
File created: 12/20/2017 In control: City Attorney's Office
On agenda: 12/20/2017 Final action: 12/20/2017
Title: Change Order No. 1 on Contract 20170051, Samuel Myers Park Restorations - Phase IV Resolved, that Change Order No. 1 on Contract 20170051, Samuel Myers Park Restoration - Phase IV, Ray Hintz Inc., contractor, as submitted, is approved in the amount of $1,731.34. Fiscal Note: Funds to defray the cost of the change order is available in 20104-57110-20063, WCMP/NOAA Samuel Myers Park Grant.
Sponsors: Terry McCarthy
Related files: 1157-17

Sponsor

Alderman McCarthy

 

Title

Change Order No. 1 on Contract 20170051, Samuel Myers Park Restorations - Phase IV

 

Resolved, that Change Order No. 1 on Contract 20170051, Samuel Myers Park Restoration - Phase IV, Ray Hintz Inc., contractor, as submitted, is approved in the amount of $1,731.34.

 

Fiscal Note: Funds to defray the cost of the change order is available in 20104-57110-20063, WCMP/NOAA Samuel Myers Park Grant.