File #: Res.09-1596    Version: A Name: Change Order No. 1 on Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, Michaels Corporation, contractor, be approved
Type: Resolution Status: Passed
File created: 9/15/2009 In control: City Attorney's Office
On agenda: Final action: 9/15/2009
Title: Change Order No. 1 on Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, Michaels Corporation, contractor, be approved Resolved, that Change Order No. 1 on Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, Michaels Corporation, contractor, as submitted, be approved in the deduct amount of $1,661.88. Fiscal Note: Change Order No. 1 will result in a decrease in contract price.
Sponsors: Gregory Helding
Related files: 09-4098
Sponsor
Alderman Helding
 
Title
Change Order No. 1 on Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, Michaels Corporation, contractor, be approved
 
Resolved, that Change Order No. 1 on Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, Michaels Corporation, contractor, as submitted, be approved in the deduct amount of $1,661.88.
 