Ricine Banner
File #: 0689-20    Version: A Name: Subject: Communication sponsored by Alder Jones on behalf of the Interim City Engineer, submitting a Change order No.1 to Contract 20190020, Reconstruction LRIP, Douglas Ave - Lalonde Contractors, Inc.
Type: Communication Status: Passed
File created: 10/9/2020 In control: Public Works and Services Committee
On agenda: 10/20/2020 Final action: 10/20/2020
Title: Subject: Communication sponsored by Alder Jones on behalf of the Interim City Engineer, submitting a Change order No.1 to Contract 20190020, Reconstruction LRIP, Douglas Ave - Lalonde Contractors, Inc. Recommendation of the Public Works and Service Committee on 10-13-20: That Change Order No. 1 to Contract 20190020, Reconstruction LRIP - Douglas Ave, Lalonde Contractors, Inc. be approved in the amount of $68,063.89 Fiscal Note: Funds are available in Org-Obj 45040-57500, Concrete Street Paving.
Attachments: 1. 20190020 Memo, Contract Change Order

Title

Subject: Communication sponsored by Alder Jones on behalf of the Interim City Engineer, submitting a Change order No.1 to Contract 20190020, Reconstruction LRIP, Douglas Ave - Lalonde Contractors, Inc.

 

Recommendation of the Public Works and Service Committee on 10-13-20:  That Change Order No. 1 to Contract 20190020, Reconstruction LRIP - Douglas Ave, Lalonde Contractors, Inc. be approved in the amount of $68,063.89

 

Fiscal Note: Funds are available in Org-Obj 45040-57500, Concrete Street Paving.