Ricine Banner
File #: 1057-24    Version: A Name: Subject: Communication sponsored by Alder Jones, on behalf of the Department of Public Works, submitting Change Order No. 2 to Contract 2024054 - Assessable Streets and Alleys, Milwaukee General Construction, Contractors. Staff Recommendation to the Pu
Type: Communication Status: Passed
File created: 11/19/2024 In control: Public Works and Services Committee
On agenda: 12/3/2024 Final action: 12/3/2024
Title: Subject: Communication sponsored by Alder Jones, on behalf of the Department of Public Works, submitting Change Order No. 2 to Contract 2024054 - Assessable Streets and Alleys, Milwaukee General Construction, Contractors. Recommendation of to the Public Works and Services Committee on 11.26.24 That Change Order No. 2 to Contract 2024054 - Assessable Streets and Alleys, Milwaukee General Construction, Contractors, be approved in the deduct amount of ($2,358.04). Fiscal Note: Funding for this change order is credited in the following Org-Objects: ($3,066.14) 45040 57515 DPW Sidewalk Replacement 708.10) 40104 57500 Concrete Alley Paving Assessable ($2,358.04) Total
Attachments: 1. CCO 2 2024054, 2. #1057-24 Resolution

Title

Subject: Communication sponsored by Alder Jones, on behalf of the Department of Public Works, submitting Change Order No. 2 to Contract 2024054 - Assessable Streets and Alleys, Milwaukee General Construction, Contractors.

 

Recommendation of to the Public Works and Services Committee on 11.26.24 That Change Order No. 2 to Contract 2024054 - Assessable Streets and Alleys, Milwaukee General Construction, Contractors, be approved in the deduct amount of ($2,358.04).

 

Fiscal Note: Funding for this change order is credited in the following Org-Objects:

($3,066.14)   45040 57515 DPW Sidewalk Replacement

708.10) 40104 57500 Concrete Alley Paving Assessable

($2,358.04) Total