File #: Res.06-7160    Version: A Name: CHANGE ORDER FOR LAKE MICHIGAN PATHWAY CONTRACT
Type: Resolution Status: Passed
File created: 8/2/2006 In control: City Attorney's Office
On agenda: Final action: 8/2/2006
Title: CHANGE ORDER FOR LAKE MICHIGAN PATHWAY CONTRACT RESOLVED, that Change Order No. 2 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $11,400.00. FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 985.913.5090, Michigan at Goold Slope Stabilization. FURTHER RESOLVED, that a time extension until September 1, 2006 to complete this contract is approved. FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-2246

Sponsor

Alderman Hart

 

Title

CHANGE ORDER FOR LAKE MICHIGAN PATHWAY CONTRACT

 

 

RESOLVED, that Change Order No. 2 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $11,400.00.

 

FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 985.913.5090, Michigan at Goold Slope Stabilization.

 

FURTHER RESOLVED, that a time extension until September 1, 2006 to complete this contract is approved.

 

 

FISCAL NOTEFunds are available as herein delineated.