Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting bid results on Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II (R1). (Res.09-1527)
Recommendation of the Public Works and Services Committee on 7-14-09: That Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II (R1), be awarded to AZAR, LLC, Racine, WI, at their bid price of $496,725.00, they being the lowest responsible bidder.
Further recommends that funding to defray the cost of this public works project be appropriated the following accounts:
$485,973.00 - Account 906.000.5520, Sidewalk Replacement
$ 352.00 - Account 989.908.5530, Crosswalk Ramps
$ 10,400.00 - Account 989.908.5320, Replacement Curb & Gutter
$496,725.00 - Total