File #: 0625-26    Version: A Name: Subject: Request for Final Payment (retainage) on Contract W-25-7, 2025 Private Lead Service Replacements, Mid City Corporation (contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-25-7 is complete at a final cost of $473,884.70
Type: Communication Status: Passed
File created: 7/8/2026 In control: Waterworks Commission
On agenda: Final action: 7/15/2026
Title: Subject: Request for Final Payment (retainage) on Contract W-25-7, 2025 Private Lead Service Replacements, Mid City Corporation (contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-25-7 is complete at a final cost of $473,884.70
Attachments: 1. 2026.07.15 - W-25-7 Final Payment Request

Title

Subject: Request for Final Payment (retainage) on Contract W-25-7, 2025 Private Lead Service Replacements, Mid City Corporation (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract W-25-7 is complete at a final cost of $473,884.70