Ricine Banner
File #: 07-0423    Version: A Name: Minor amendment to the Pointe Blue planned development in the 1100 block of Michigan Blvd.
Type: Communication Status: Committee Report To Council
File created: 4/5/2007 In control: City Plan Commission
On agenda: Final action: 4/16/2007
Title: Subject: Request by Scott Fergus of KeyBridge Development Group for a minor amendment to the Pointe Blue planned development in the 1100 block of Michigan Blvd. seeking the extension of the final plan submittal deadline to allow for project phasing. Recommendation of City Plan Commission on 4-11-07: That the request of Key Bridge Development Group, dated March 25, 2007 and presented to the City Plan Commission on April 11, 2007, for a minor amendment to the planned development for Pointe Blue to address filing deadlines for the submittal of final plans, be approved subject to the following: a. That all aspects of this planned development proceed in compliance with Common Council Resolution 06-7121 of September 5, 2006, unless otherwise varied herein. b. That the Final Plan for Infrastructure (with accompanying construction schedule) be submitted to the City Plan Commission no later than July 25, 2007. c. That the Final Plan for High Rise Tower 3 (eastern most tower) be submitted t...
Related files: Res.07-0188
Title
Subject: Request by Scott Fergus of KeyBridge Development Group for a minor amendment to the Pointe Blue planned development in the 1100 block of Michigan Blvd. seeking the extension of the final plan submittal deadline to allow for project phasing.

Recommendation of City Plan Commission on 4-11-07: That the request of Key Bridge Development Group, dated March 25, 2007 and presented to the City Plan Commission on April 11, 2007, for a minor amendment to the planned development for Pointe Blue to address filing deadlines for the submittal of final plans, be approved subject to the following:

a. That all aspects of this planned development proceed in compliance with Common Council Resolution 06-7121 of September 5, 2006, unless otherwise varied herein.

b. That the Final Plan for Infrastructure (with accompanying construction schedule) be submitted to the City Plan Commission no later than July 25, 2007.

c. That the Final Plan for High Rise Tower 3 (eastern most tower) be submitted to the City Plan Commission no later than October 31, 2007.

d. That the Final Plan for Mid Rise Tower 2 (just west of the High Rise Tower) be submitted to the City Plan Commission no later than October 31, 2008.

e. That the Final Plan for Mid Rise Tower 1 (just west of Mid Rise Tower 2) be submitted to the City Plan Commission no later than October 31, 2009.

f. That the Final Plan for the low-rise units bounded on the east by William Lewis Lane and on the west by Lindsay Lane be submitted to the City Plan Commission no later than November 30, 2007.

g. That the Final Plan for the low-rise construction bounded on the east by Lindsay Lane and on the west by Maggie Lane be submitted to the City Plan Commission by July 31, 2008.

h. That the Final Plan for the low-rise construction bounded on the east by Maggie Lane and on the west Michigan Blvd. be submitted to the City Plan Commission no later than November 30, 2008.

i. That the Final Plan for the Coast Guard buildings be subm...