Sponsor
Alderman Helding
Title
Change Order No. 2 on Contract 09-09 (K9-009), 2009 Concrete Street Reconstruction, LaLonde Contractors, be approved
Resolved, that Change Order No. 2 on Contract 9-09 (K9-009), 2009 Concrete Street Reconstruction, LaLonde Contractors, contractor, be approved in the amount of $130,773.88.
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
$101,824.60 - Account 989.908.5020, Conc. Pvmt. Repl. Misc. Loc.
$ 9,984.28 - Account 988.908.5020, Conc. Pvmt. Repl. Misc. Loc.
$ 18,965.00 - Account 104.900.5420, Storm Sewer, Misc. Loc.
$130,773.88 - Total
Fiscal Note: Funds are available as herein delineated.