Ricine Banner
File #: Res.09-1539    Version: A Name: Change Order No. 6, Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc., be approved
Type: Resolution Status: Passed
File created: 8/3/2009 In control: City Attorney's Office
On agenda: Final action: 8/3/2009
Title: Change Order No. 6, Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc., be approved Resolved, that Change Order No. 6 on Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $30,943.00. Further resolved, that funding to defray the cost of this change order be appropriated from Account 988.100.5010, City Hall-Facilities Plan Implementation. Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 09-3852
Sponsor
Alderman Helding
 
Title
Change Order No. 6, Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc., be approved
 
Resolved, that Change Order No. 6 on Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $30,943.00.
 
Further resolved, that funding to defray the cost of this change order be appropriated from Account 988.100.5010, City Hall-Facilities Plan Implementation.
 
Fiscal Note: Funds are available as herein delineated.