Ricine Banner
File #: Res.0231-18    Version: A Name: Change Order No. 1 on Contract 20180001 - HDPE Conduit & Fiber Extension to North Beach Oasis Building
Type: Resolution Status: Passed
File created: 7/17/2018 In control: City Attorney's Office
On agenda: 7/17/2018 Final action: 7/17/2018
Title: Change Order No. 1 on Contract 20180001 - HDPE Conduit & Fiber Extension to North Beach Oasis Building Resolved, that Change Order No. 1 on Contract 20180001, HDPE Conduit & Fiber Extension to North Beach Oasis Building, Jet Underground, LLC., contractor, is approved in the amount of $11,264.08. Fiscal Note: Funding to defray the cost of the change order be appropriated from the below Org-Objects: $ 7,446.32 - Org-Object 70113-57355, Computer Hardware $ 3,817.76 - Org-Object 14012-53200, Electrical Supplies & Repairs $11,264.08 - Total
Sponsors: John Tate II
Related files: 0668-18

Sponsor

Alderman Tate

 

Title

Change Order No. 1 on Contract 20180001 - HDPE Conduit & Fiber Extension to North Beach Oasis Building

 

Resolved, that Change Order No. 1 on Contract 20180001, HDPE Conduit & Fiber Extension to North Beach Oasis Building, Jet Underground, LLC., contractor, is approved in the amount of $11,264.08.

 

Fiscal Note: Funding to defray the cost of the change order be appropriated from the below Org-Objects:

 

$  7,446.32 - Org-Object 70113-57355, Computer Hardware

$  3,817.76 - Org-Object 14012-53200, Electrical Supplies & Repairs

$11,264.08 - Total