File #: 10-4878    Version: A Name: Bid results on Contract 16-10 (K0-016), 2010 Sidewalk Replacement-Phase I.
Type: Communication Status: Passed
File created: 3/16/2010 In control: Public Works and Services Committee
On agenda: Final action: 4/7/2010
Title: Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting bid results on Contract 16-10 (K0-016), 2010 Sidewalk Replacement-Phase I. (Res.10-1945) Recommendation of the Public Works and Services Committee on 3-30-10: That Contract 16-10 (K0-016), 2010 Sidewalk Replacement-Phase I, be awarded to AZAR, LLC, Racine, WI, at their bid price of $142,245.70, they being the lowest responsible bidder. Further recommends that funding to defray the cost of this public works project be appropriated from the following accounts: $132,245.70 - Account 906.000.5520, Sidewalk Replacement $ 10,000.00 - Account 990.908.5520, Sidewalk Replacement $142,245.70 - Total Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 16-10 Bid Results.pdf, 2. 16-10 2010 Sidewalk Replacement - Phase I.pdf
Related files: Res.10-1945
Title
Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting bid results on Contract 16-10 (K0-016), 2010 Sidewalk Replacement-Phase I.  (Res.10-1945)
 
Recommendation of the Public Works and Services Committee on 3-30-10: That Contract 16-10 (K0-016), 2010 Sidewalk Replacement-Phase I, be awarded to AZAR, LLC, Racine, WI, at their bid price of $142,245.70, they being the lowest responsible bidder.
 
Further recommends that funding to defray the cost of this public works project be appropriated from the following accounts:
 
$132,245.70 - Account 906.000.5520, Sidewalk Replacement
$  10,000.00 - Account 990.908.5520, Sidewalk Replacement
$142,245.70 - Total
 
Fiscal Note: Funds are available as herein delineated.