Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 2 on Contract 10-10 (K0-010), 2010 Republic Avenue Reconstruction CDBG, A.W. Oakes and Son, contractor. (Res.10-2340)
Recommendation of the Public Works and Services Committee on 12-14-10: That Change Order No. 2 on Contract 10-10 (K0-010), 2010 Republic Avenue Reconstruction CDBG, A.W. Oakes & Son, Inc., contractor, as submitted, be approved in the deduct amount of $20,855.31.
Further recommends that the funding accounts be adjusted by the following amounts:
($14,058.31) - Account 890.030.5540, 2010 Street Resurfacing
($ 1,360.00) - Account 287.990.5310, Sanitary Sewer Var. Locations
($ 5,437.00) - Account 104.990.5420, Storm Sewer Misc. Locations
($20,855.31) - Total
Fiscal Note: Change Order No. 2 will result in a decrease in contract price.