Ricine Banner
File #: 07-0216    Version: A Name: Traffic signal study for State Project ID: 2703-03-05/75, Ohio Street from 16th Street to 21st Street.
Type: Communication Status: Passed
File created: 2/21/2007 In control: Public Works and Services Committee
On agenda: Final action: 3/6/2007
Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering submitting the traffic signal study for State Project ID: 2703-03-05/75, Ohio Street from 16th Street to 21st Street. Recommendation: The traffic signal study for State Project ID: 2703-03-05/75, Ohio Street from 16th Street to 21st Street be accepted. Further recommends that traffic signals be installed at the intersection of Ohio Street and Byrd Avenue and that the pedestrian overpass be removed as part of the Ohio Street reconstruction project. Fiscal Note: The State of Wisconsin will pay 80% of the cost for the installation of the signals and razing of the pedestrian overpass.
Attachments: 1. DOC070221
Title
Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering submitting the traffic signal study for State Project ID:  2703-03-05/75, Ohio Street from 16th Street to 21st Street.
 
Recommendation: The traffic signal study for State Project ID:  2703-03-05/75, Ohio Street from 16th Street to 21st Street be accepted.
 
Further recommends that traffic signals be installed at the intersection of Ohio Street and Byrd Avenue and that the pedestrian overpass be removed as part of the Ohio Street reconstruction project.
 
Fiscal Note: The State of Wisconsin will pay 80% of the cost for the installation of the signals and razing of the pedestrian overpass.