Ricine Banner
File #: Res.15-0112    Version: A Name: Change Order No. 1 to Contract 07-14 (K4-007), 2014 CDBG Concrete Reconstruct
Type: Resolution Status: Passed
File created: 3/17/2015 In control: Common Council
On agenda: Final action: 3/17/2015
Title: Change Order No. 1 to Contract 07-14 (K4-007), 2014 CDBG Concrete Reconstruct Resolved, that Change Order No. 1 on Contract 07-14 (K4-007), 2014 CDBG Concrete Reconstruct, A.W. Oakes & Son, Inc., contractor, as submitted, is approved in the deduct amount of ($9,585.99). Fiscal Note: Funding Org-Objects be adjusted by the following amounts: $ 26,027.35 - 994.908.5020 (Org-Object 45040-57500, Concrete Pvmt., Rpl. Misc./DPW-Paving) ($ 10,381.43) - 287.994.5310 (Org-Object 22640-57560, San. Sewers, Var. Loc./San. Sewers) ($ 49,089.41) - 994.000.5050 (Org-Object 40101-57560, CDBG Sanitary Fund/Sanitary Sewers) $ 23,857.50 - 104.994.5420 (Org-Object 60484-57570, Storm Sewers Misc./Storm Sewers) ($ 9,585.99) - Total
Sponsors: Jim Kaplan
Related files: 15-00210
Sponsor
Alderman Kaplan
 
Title
Change Order No. 1 to Contract 07-14 (K4-007), 2014 CDBG Concrete Reconstruct
 
Resolved, that Change Order No. 1 on Contract 07-14 (K4-007), 2014 CDBG Concrete Reconstruct, A.W. Oakes & Son, Inc., contractor, as submitted, is approved in the deduct amount of
($9,585.99).
 
Fiscal Note: Funding Org-Objects be adjusted by the following amounts:
 
$  26,027.35 - 994.908.5020 (Org-Object 45040-57500, Concrete Pvmt., Rpl. Misc./DPW-Paving)
($ 10,381.43) - 287.994.5310 (Org-Object 22640-57560, San. Sewers, Var. Loc./San. Sewers)
($ 49,089.41) - 994.000.5050 (Org-Object 40101-57560, CDBG Sanitary Fund/Sanitary Sewers)
$  23,857.50 - 104.994.5420 (Org-Object 60484-57570, Storm Sewers Misc./Storm Sewers)
($   9,585.99) - Total