File #: Res.0088-18    Version: A Name: Change Order No. 1 on Contract 20170019 - 2017 Parking Lots
Type: Resolution Status: Passed
File created: 3/20/2018 In control: City Attorney's Office
On agenda: 3/20/2018 Final action: 3/20/2018
Title: Change Order No. 1 on Contract 20170019 - 2017 Parking Lots Resolved, that Change Order No. 1 on Contract 20170019 - 2017 Parking Lots, Payne & Dolan, Inc., contractor, as submitted, is approved in the deduct amount of ($7,209.51). Fiscal Note: Funding accounts be adjusted by the following amounts: $ 4,804.20 - Org-Object 60383-57500, Parking System - Paving ($12,013.71) - Org-Object 45050-57110, Myers Pave Circle Drive ($ 7,209.51) - Total
Sponsors: Terry McCarthy
Related files: 0237-18

Sponsor

Alderman McCarthy

 

Title

Change Order No. 1 on Contract 20170019 - 2017 Parking Lots

 

Resolved, that Change Order No. 1 on Contract 20170019 - 2017 Parking Lots, Payne & Dolan, Inc., contractor, as submitted, is approved

in the deduct amount of ($7,209.51).

 

Fiscal Note: Funding accounts be adjusted by the following amounts:

 

$   4,804.20 - Org-Object 60383-57500, Parking System - Paving

($12,013.71) - Org-Object 45050-57110, Myers Pave Circle Drive

($ 7,209.51) - Total