File #:
|
0533-21
Version:
A
|
Name:
|
Subject: Communication sponsored by Alder Jones, on behalf of City Engineer, submitting Change Order No. 1 to Contract 2021003-Sidewalk Replacement-Phase 1, Forward Equipment, LLC, Contractor
|
Type:
|
Communication
|
Status:
|
Passed
|
On agenda:
|
|
Final action:
|
7/20/2021
|
Title:
|
Subject: Communication sponsored by Alder Jones, on behalf of City Engineer, submitting Change Order No. 1 to Contract 2021003-Sidewalk Replacement-Phase 1, Forward Equipment, LLC, Contractor
Recommendation of the Public Works and Services Committee on 7-13-21: That Change Order No. 1 to Contract 2021003-Sidewalk Replacement-Phase 1, Forward Equipment, LLC, Contractor be approved in the deduct amount of ($38,212.90).
Fiscal Note: Funding for this change order is credited in the following Org-Objects: 40104-57515-Sidewalk Assessment.
|
Title
Subject: Communication sponsored by Alder Jones, on behalf of City Engineer, submitting Change Order No. 1 to Contract 2021003-Sidewalk Replacement-Phase 1, Forward Equipment, LLC, Contractor
Recommendation of the Public Works and Services Committee on 7-13-21: That Change Order No. 1 to Contract 2021003-Sidewalk Replacement-Phase 1, Forward Equipment, LLC, Contractor be approved in the deduct amount of ($38,212.90).
Fiscal Note: Funding for this change order is credited in the following Org-Objects: 40104-57515-Sidewalk Assessment.
|