Sponsor
Alderman Hart
Title
Contract award for City Hall renovations
Resolved, that Contract 1-07 (K7-001), City Hall Renovations, Phase I (R1), be awarded to Seater Construction Co., Inc., Racine, WI, at its bid price of $542,000.00, plus Alternate #1 in the amount of $4,906.00, for a total contract amount of $546,906.00, it being the lowest responsible bidder.
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
$ 64,674.00 - Account 985.100.5010, City Hall Window Replacement
$ 47,000.00 - Account 985.100.5020, City Hall HVAC Upgrade
$435,232.00 - Account 986.100.5010, Facility Plan Implementation
$546,906.00 - Total
Fiscal Note: Funds are available as herein delineated.