Sponsor
Alderman Kaplan
Title
Final Payment on Contract 09-14 (K4-009), 2014 Street & Alley Paving - Northside Assessable (R1)
Resolved, that the work done by Milwaukee General Construction Company, Inc. under Contract 09-14 (K4-009), 2014 Street & Alley Paving - Northside Assessable (R1), is accepted and final payment authorized for a total contract amount of $630,222.68.
Fiscal Note: Contract was authorized under Resolution 14-0218, dated May 20, 2014.