Title:
|
Subject: (Direct Referral) Change Order #4 Contract 52-07 (K7-061), Remodel Racine Zoological Gardens, Phase III, by Seater Construction Co., Inc.
Recommendation of the Public Safety & Licensing Committee on 06-09-08: The work of Seater Construction Co., Inc. on Contract 52-07(K7-061), Remodel Racine Zoological Gardens, Phase III, be accepted in the increased amount of $54,436.00.
Fiscal Note: Funds are available in account 987.740.503, Entrance Complex/Parking
|