File #: Res.06-7028    Version: A Name: CHANGE ORDER RACINE RAILROAD DEPOT RESTORATION
Type: Resolution Status: Passed
File created: 5/16/2006 In control: City Attorney's Office
On agenda: Final action: 5/16/2006
Title: CHANGE ORDER RACINE RAILROAD DEPOT RESTORATION RESOLVED, that Change Order No. 3 on Contract 25-04 (K4-035), Racine Railroad Depot Restoration, Tri-North Builders, Inc., contractor, as submitted, be approved in the amount of $78,646.77. FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 105.900.5010, Capital Projects. FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-1879

Sponsor

Alderman Hart

 

Title

CHANGE ORDER RACINE RAILROAD DEPOT RESTORATION

 

RESOLVED, that Change Order No. 3 on Contract 25-04 (K4-035), Racine Railroad Depot Restoration, Tri-North Builders, Inc., contractor, as submitted, be approved in the amount of $78,646.77.

 

FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 105.900.5010, Capital Projects.

 

 

FISCAL NOTEFunds are available as herein delineated.