File #: Res.07-0362    Version: A Name: Change Order for Contract Pritchard/Reservoir Park Pond Retrofit
Type: Resolution Status: Passed
File created: 8/6/2007 In control: City Attorney's Office
On agenda: Final action: 8/6/2007
Title: Change Order for Contract Pritchard/Reservoir Park Pond Retrofit Resolved, that Change Order No. 2 to Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, K & L Construction, contractor, as submitted, be approved in the amount of $89,837.08. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $25,916.08 - Account 104.987.5420, Storm Sewers, Various Locations $15,000.00 - Account 987.908.5130, Asphalt Resurfacing $15,000.00 - Account 987.908.5020, Concrete Pavement Replacement, Misc. $33,921.00 - Account 970.000.5060, TID #10 - Planning $89,837.08 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 07-0979
Sponsor
Alderman Hart
 
Title
Change Order for Contract Pritchard/Reservoir Park Pond Retrofit
 
 
Resolved, that Change Order No. 2 to Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, K & L Construction, contractor, as submitted, be approved in the amount of $89,837.08.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$25,916.08 - Account 104.987.5420, Storm Sewers, Various Locations
$15,000.00 - Account 987.908.5130, Asphalt Resurfacing
$15,000.00 - Account 987.908.5020, Concrete Pavement Replacement, Misc.
$33,921.00 - Account 970.000.5060, TID #10 - Planning
$89,837.08 - Total
 
 
Fiscal Note: Funds are available as herein delineated.