Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Engineering, submitting Change Order No. 1 on Contract 16-10 (K0-016), 2010 Sidewalk Replacement, Phase I, AZAR, LLC, contractor. (Res. 11-2620)
Recommendation of the Public Works and Services Committee on 6-14-11: That Change Order No. 1 on Contract 16-10 (K0-016), 2010 Sidewalk Replacement, Phase I, AZAR, LLC, contractor, be approved in the amount of $24,275.48.
Further recommends that funding to defray the cost of this change order be appropriated from Account 906.000.5520, Sidewalk Replacement.