File #: Res.15-0465    Version: A Name: Change Order No. 2 to Contract 20150039, 2015 Sanitary Sewer - Echo Lane (R1)
Type: Resolution Status: Passed
File created: 12/15/2015 In control: City Attorney's Office
On agenda: 12/15/2015 Final action: 12/15/2015
Title: Change Order No. 2 to Contract 20150039, 2015 Sanitary Sewer - Echo Lane (R1) Resolved, that Change Order No. 2 on Contract 20150039, 2015 Sanitary Sewer - Echo Lane (R1), A.W. Oakes & Son, Inc., contractor, as submitted, is approved in the amount of $79,667.06. Fiscal Note: Funding to defray the cost of the change order be appropriated from the following Org-Objects: $39,472.00 - Org-Object 40102-57560, RWWU-Sewer Relay $20,165.00 - Org-Object 22640-57560, Sanitary Sewer $20,030.06 - Org-Object 60484-57570, Storm Sewer $79,667.06- Total
Sponsors: James Morgenroth
Related files: 15-01038

Sponsor

Alderman Morgenroth

 

Title

Change Order No. 2 to Contract 20150039, 2015 Sanitary Sewer - Echo Lane (R1)

 

Resolved, that Change Order No. 2 on Contract 20150039, 2015 Sanitary Sewer - Echo Lane (R1), A.W. Oakes & Son, Inc., contractor, as submitted, is approved in the amount of $79,667.06.

 

Fiscal Note: Funding to defray the cost of the change order be appropriated from the following Org-Objects:

$39,472.00 - Org-Object 40102-57560, RWWU-Sewer Relay

$20,165.00 - Org-Object 22640-57560, Sanitary Sewer

$20,030.06 - Org-Object 60484-57570, Storm Sewer