File #: 07-1331    Version: A Name: Change Order No. 6 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II
Type: Communication Status: Passed
File created: 10/22/2007 In control: Public Works and Services Committee
On agenda: Final action: 11/6/2007
Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 6 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor. Recommendation: That Change Order No. 6 on Contract 49-05 (K5-056), Lake Michigan Pathway - Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $9,293.50. Further recommends that funding to defray the cost of this change order be appropriated from Account 987.908.5130, Asphalt Resurfacing. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. Ald Hart - CO 6-49-05, 2. CO #6-49-05
Related files: Res.07-0492

Title

Subject:  Direct Referral.  Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 6 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor.

 

Recommendation: That Change Order No. 6 on Contract 49-05 (K5-056), Lake Michigan Pathway - Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $9,293.50.

 

Further recommends that funding to defray the cost of this change order be appropriated from Account 987.908.5130, Asphalt Resurfacing.

 