File #: 11-6061    Version: A Name: Change Order No. 1 on Contract 19-10 (K0-019), 2010 City Resurfacing (R1), Stark Asphalt, contractor.
Type: Communication Status: Passed
File created: 2/9/2011 In control: Public Works and Services Committee
On agenda: Final action: 3/1/2011
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 1 on Contract 19-10 (K0-019), 2010 City Resurfacing (R1), Stark Asphalt, contractor. (Res.11-2423) Recommendation of the Public Works and Services Committee on 2-23-11: That Change Order No. 1 on Contract 19-10 (K0-019), 2010 City Resurfacing (R1), Stark Asphalt, contractor, as submitted, be approved in the deduct amount of $22,223.58. Further recommends that the funding accounts be adjusted by the following amounts: ($24,649.23) - Account 990.908.5220, Asphalt Resurfacing $ 1,298.50 - Account 104.990.5420, Storm Sewer Misc. Loc. $ 1,100.00 - Account 287.990.5310, Sanitary Sewer, Var. Loc. $ 27.15 - Account 989.590.5010, Replace City Circuits ($22,223.58) - Total Fiscal Note: Change Order No. 1 will result in a decrease in contract price.
Attachments: 1. 11-6061
Related files: Res.11-2423
Title
Subject:  (Direct Referral) Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 1 on Contract 19-10 (K0-019),  2010 City Resurfacing (R1), Stark Asphalt, contractor.  (Res.11-2423)
 
Recommendation of the Public Works and Services Committee on 2-23-11: That Change Order No. 1 on Contract 19-10 (K0-019), 2010 City Resurfacing (R1), Stark Asphalt, contractor, as submitted, be approved in the deduct amount of $22,223.58.
 
Further recommends that the funding accounts be adjusted by the following amounts:
 
($24,649.23) - Account 990.908.5220, Asphalt Resurfacing
$   1,298.50 - Account 104.990.5420, Storm Sewer Misc. Loc.
$   1,100.00 - Account 287.990.5310, Sanitary Sewer, Var. Loc.
$        27.15 - Account 989.590.5010, Replace City Circuits
($22,223.58) - Total
 
Fiscal Note:  Change Order No. 1 will result in a decrease in contract price.