Ricine Banner
File #: Res.10-2170    Version: A Name: Change Order No. 1 on Contract 13-10 (K0-013), 2010 North Side Street Paving (R1), Milwaukee General Construction Co., Inc., contractor, be approved
Type: Resolution Status: Passed
File created: 9/7/2010 In control: City Attorney's Office
On agenda: Final action: 9/7/2010
Title: Change Order No. 1 on Contract 13-10 (K0-013), 2010 North Side Street Paving (R1), Milwaukee General Construction Co., Inc., contractor, be approved Resolved, that Change Order No. 1 on Contract 13-10 (K0-013), 2010 North Side Street Paving (R1), Milwaukee General Construction Co., Inc., contractor, be approved in the amount of $56,097.68. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $ 52,157.68 - Account 990.908.5020, Conc. Pvmt. Repl. Misc. Locations $ 3,940.00 - Account 104.990.5420, Storm Sewers, Misc. Locations $ 56,097.68 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 10-5515
Sponsor
Alderman Helding
 
Title
Change Order No. 1 on Contract 13-10 (K0-013), 2010 North Side Street Paving (R1), Milwaukee General Construction Co., Inc., contractor, be approved
 
Resolved, that Change Order No. 1 on Contract 13-10 (K0-013), 2010 North Side Street Paving (R1), Milwaukee General Construction Co., Inc., contractor, be approved in the amount of $56,097.68.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$ 52,157.68 - Account 990.908.5020, Conc. Pvmt. Repl. Misc. Locations
$  3,940.00 - Account 104.990.5420, Storm Sewers, Misc. Locations
$ 56,097.68 - Total
 
Fiscal Note:  Funds are available as herein delineated.