File #: Res.08-0978    Version: A Name: Change Order No. 2 on Contract for BUS Administrative Office Expansion
Type: Resolution Status: Passed
File created: 8/19/2008 In control: City Attorney's Office
On agenda: Final action: 8/19/2008
Title: Change Order No. 2 on Contract for BUS Administrative Office Expansion Resolved, that Change Order No. 2 on Contract 2-08 (K8-002), BUS Administrative Office Expansion, Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $39,367.00. Further resolved, that funds to defray the cost of this change order be appropriated from Account 105.900.5010, Capital Projects. Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 08-2519
Sponsor
Alderman Helding
 
Title
Change Order No. 2 on Contract for BUS Administrative Office Expansion
 
Resolved, that Change Order No. 2 on Contract 2-08 (K8-002), BUS Administrative Office Expansion, Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $39,367.00.
 
Further resolved, that funds to defray the cost of this change order be appropriated from Account 105.900.5010, Capital Projects.
 
Fiscal Note:  Funds are available as herein delineated.