Title
Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting a request for final payment on Contract 14-08 (K8-015), Street Paving, John's Concrete, contractor. (Res.09-1292)
Recommendation of the Public Works and Services Committee on 3-10-09: The work done by John's Concrete, Inc. under Contract 14-08 (K8-015), Street Paving, be accepted and final payment authorized for a total contract amount of $409,548.07.
Fiscal Note: Contract was authorized under Resolution No. 08-0730, dated April 2, 2008.