Skip to main content
Ricine Banner
File #: 0628-25    Version: A Name: Subject: Consideration of Change Order No. 1 on Contract W-25-2, 2025 Water Main Replacement - Phase 1, Earth X, LLC (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $29,160.00, bringing the total
Type: Communication Status: Passed
File created: 6/12/2025 In control: Waterworks Commission
On agenda: Final action: 6/18/2025
Title: Subject: Consideration of Change Order No. 1 on Contract W-25-2, 2025 Water Main Replacement - Phase 1, Earth X, LLC (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $29,160.00, bringing the total contract amount to $981,435.00.
Attachments: 1. w-25-2_co#1_ltr to commsrs

Title

Subject: Consideration of Change Order No. 1 on Contract W-25-2, 2025 Water Main Replacement - Phase 1, Earth X, LLC (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an increase of $29,160.00, bringing the total contract amount to $981,435.00.