Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 1 on Contract 30-14 (K4-030), Central Heating Plant - Steam Pipe Replacement (R1), United Mechanical, Inc., contractor. (Res No. 15-0005)
Recommendation of the Public Works and Services Committee on 01-13-15: That Change Order No. 1 on Contract 30-14 (K4-030), Central Plant - Steam Pipe Replacement (R1), United Mechanical, Inc., contractor, as submitted, be approved in the amount of $17,890.
Further recommends that funding to defray the cost of this change order be appropriated from Account 994.220.5010 (Org-Object 45040-57200), DPW Building Improvements.