File #: 09-4099    Version: A Name: Final payment on Contract 33-08 (K8-036), 2008 Sanitary Sewer Lining
Type: Communication Status: Passed
File created: 9/2/2009 In control: Public Works and Services Committee
On agenda: Final action: 9/15/2009
Title: Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting a request for final payment on Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, Michel's Corporation, contractor. (Res.09-1597) Recommendation of the Public Works and Services Committee on 9-08-09: The work done by Michaels Corporation under Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, be accepted and final payment authorized for a total contract amount of $731,279.12. Fiscal Note: Contract was authorized under Resolution No. 08-0880, dated June 17, 2008.
Attachments: 1. Ald Helding - Final-33-08
Related files: Res.09-1597
Title
Subject:  (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting a request for final payment on Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, Michel's Corporation, contractor.  (Res.09-1597)
 
Recommendation of the Public Works and Services Committee on 9-08-09: The work done by Michaels Corporation under Contract 33-08 (K8-037), 2008 Sanitary Sewer Lining, be accepted and final payment authorized for a total contract amount of $731,279.12.
 
Fiscal Note: Contract was authorized under Resolution No. 08-0880, dated June 17, 2008.